The Hongkong Electric
Company Limited (HEC) supplies Hong Kong
Island and the neighbouring islands of
Ap Lei Chau and Lamma; CLP Power Hong
Kong Limited (CLP Power) supplies Kowloon
and the New Territories, including Lantau
and several outlying islands. The supply
to consumers is at 50Hz alternating current
while the voltage is 220 volts single-phase
and 380 volts three-phase.
The two supply companies
are investor-owned. The Government monitors
the two companies through mutually agreed
Scheme of Control Agreements. Current
agreements with CLP Power and HEC came
into effect on October 1, 1993, and January
1, 1994, respectively. Both will last
for 15 years. The first and second five-yearly
interim reviews were completed in early
1999 and late 2003. The agreements require
each company to seek the approval of the
Government for certain aspects of their
financial plans, including projected tariff
levels. The agreements do not grant the
companies any exclusive rights. They are
not franchises, nor do they define a supply
area for either company or exclude new
entrants to the market.
At year-end, HEC had
a total installed capacity of 3 420
megawatts (MW) at the Lamma Power Station.
Its first 300MW gas combined-cycle generator
at the new Lamma Extension Power Station
is scheduled to start commercial operation
in 2006.
The Castle Peak Power
Company Limited (CAPCO) supplies electricity
to CLP Power from its Black Point (2 188MW),
Castle Peak (4 108MW) and Penny's
Bay (300MW) power stations. The eighth
312.5MW generator is scheduled to go into
operation at Black Point in 2006.
CLP Power and HEC own
their respective transmission and distribution
systems. The two transmission systems
are interconnected by a cross-harbour
link. This provides emergency back-up
and achieves cost savings to consumers
through economic energy transfers between
the two systems and a reduction in the
amount of generating capacity that needs
to be kept as spinning reserve against
the tripping of other units. The interconnection
link currently has a total capacity of
720 megavolt-amperes (MVA) (i.e. 720 000
kilovolt-amperes (kVA)).
CLP Power's transmission
system is also interconnected with the
electricity network in Guangdong Province
which facilitates the export and import
of electricity to and from the province.
The electricity sales to Guangdong are
made from existing reserve generating
capacity of CLP Power and are governed
by an agreement with the Government, under
which CLP Power's consumers receive priority
of supply and 80 per cent of the profit
from the sales. At the same time, CLP
Power buys about 70 per cent of the power
generated by the Guangdong Nuclear Power
Station at Daya Bay, which has two 984
MW pressurised water reactors, to meet
part of the longer-term demand for electricity
in its supply area.
CLP Power also has the
right to use 50 per cent of the 1 200MW
capacity of Phase 1 of the Guangzhou Pumped
Storage Power Station, at Conghua. Off-peak
electricity from the CAPCO system and
the Guangdong Nuclear Power Station is
stored in the pumped storage power station,
which generates hydro-electricity to meet
Hong Kong's peak demand.
The Electricity Ordinance
is the main enabling legislation on electrical
safety. Under this ordinance, there are
regulations concerning registration of
electrical contractors and workers and
competent persons, safety of electrical
wiring, supply of safe household electrical
products and protection of electricity
supply lines from third party damage.
As at December 2005,
some 8 700 electrical contractors
and 64 500 electrical workers held
valid registration. Also, some 590 competent
persons had been approved for locating
underground electricity cables. In 2005,
the Electrical and Mechanical Services
Department revised the code of practice
on working near electricity supply lines
to provide up-to-date guidelines on how
to comply with the requirements of the
Electricity Supply Lines (Protection)
Regulation. During enforcement of
the Electricity Ordinance in 2005, the
Government conducted some 12 200
site inspections to check the safety standards
of electrical installations and electrical
product supply outlets and works sites
near electricity supply lines. Prosecution
action was initiated in 374 cases. |