Flood Prevention
Infrastructure
The Drainage Services
Department is working on a series of major
flood control projects in the northwestern
and northern parts of the New Territories
and in West Kowloon, costing about $12.3
billion.
In the northwestern
New Territories, improvement works to
26.5 kilometres of the major river network
have been completed, covering Shan Pui
River, Kam Tin River and Ngau Tam Mei
main drainage channel. As a result, the
flood risk in the surrounding areas has
been reduced.
Construction of Yuen
Long Bypass Floodway and San Tin eastern
main drainage channel is in progress.
When the work is finished in 2006, the
flooding problem in areas of Yuen Long
New Town and east of San Tin will be resolved.
Planning and design work for San Tin western
drainage channel is under way.
In the northern New
Territories, the critical flood mitigation
undertakings include Shenzhen River Regulation
Project Stage III, which involves training
four kilometres of river channel from
Lo Wu to its confluence with Ping Yuen
River, is due for completion by the end
of 2006.
Improvement work on
1.7 kilometres of Ping Yuen River to tackle
the flooding problem in Ta Kwu Ling will
be finished by early 2006, while work
on 1.8 kilometres of Ma Wat River in Kau
Lung Hang, Tai Po North, is due for completion
by the end of 2008. Design work for another
19.5 kilometres of drainage channels in
the northern New Territories, including
upstream portions of Ping Yuen, Sheung
Yue and Ng Tung Rivers, is also in hand.
Upon completion of these remaining river
training works, the regional flooding
problem in the northern New Territories
will be overcome.
There are 25 village
flood pumping schemes in operation to
protect low-lying villages from flooding.
These schemes involve constructing a bund
around a low-lying village and pumping
storm water from the area within the bund
to an outside channel during rainstorms.
Similar schemes for Shui Pin Tsuen and
Tai Kiu are under construction.
In West Kowloon, the
construction of the large flood storage
tank underneath Tai Hang Tung Recreation
Ground and the stormwater transfer tunnel
from Kowloon Tong to Kai Tak Nullah, were
completed. The Stage III works, which
include the laying of about 12 kilometres
of stormwater drains in Yau Ma Tei, Sham
Shui Po, Kowloon Tong and Yau Yat Tsuen,
are due to be finished in 2007. On completion,
the flood risks in West Kowloon will be
substantially reduced. Implementation
of the Lai Chi Kok Transfer Scheme is
being planned to further raise the flood
protection level in Lai Chi Kok, Cheung
Sha Wan and Sham Shui Po to the required
standard.
Serious flooding was
recorded in Hong Kong North in past rainy
seasons. The department is planning to
build the Hong Kong West Drainage Tunnel,
which consists of a 6.25 metre diameter
section of 4.5 kilometres from Tai Hang
to Aberdeen, and a 7.25 metre diameter
section of 6 kilometres from Aberdeen
to Pok Fu Lam. It includes a total of
36 flow intakes for intercepting flows
from the upper catchments for discharge
into the sea at Pok Fu Lam. This tunnel
will help reduce the flood risks at the
lower catchments — and hence the
hazard of overland flows down steep roads
in Mid-Levels — and the scale of
the online drainage improvement works
in the lower catchments. Preliminary design
and investigation consultancy work is
close to completion, while detailed design
and construction will be awarded soon.
The department has completed
eight Drainage Master Plan Studies since
1994 to review the condition and performance
of the existing stormwater drainage systems
in various flood-prone areas throughout
Hong Kong. In view of current and future
development needs, further packages of
improvement works with greater focus on
the secondary drainage networks have been
included in the Public Works Programme
and are at different stages of planning,
design and construction.
Under a preventive maintenance
programme, the public drainage system
is regularly inspected and desilted before
and during the rainy seasons to ensure
that stormwater is discharged.
In 2005, the department
maintained 2 537 kilometres of watercourses,
river channels and drains, from which
40 077 cubic metres of silt were
removed. The importance of flood
prevention is promoted through various
public education activities. Promotional
pamphlets and advisory notes are distributed
to villagers and property management offices
before the rainy season. In addition,
the department has received students at
the San Tin Flood Prevention Information
Centre and organised site visits for district
councillors and the media to promote their
understanding of the department's work
and thereby enhance public awareness of
flood prevention. |